Roosevelt Avenue - 6th Street to 12th Street Reconstruction

Project Type:
Street
Project Status: 
Approved and Under Construction
Location: 
Roosevelt Avenue
6th Street - 12th Street
Two Rivers, WI 54241

July 30, 2024 Update
-Completed water services and sanitary sewer laterals on July 29
-All properties are now on the new water main and temporary water service is currently being dismantled.
-Currently working on storm sewer main and storm service laterals.  Expect to complete storm sewer work in the next two weeks.
-Grading and graveling operations are expected to start the week of August 12
 

July 8, 2024 Update 
- Completed installation of sanitary sewer main (12th Street to Lowell Street)
- Continue installation of water main from 9th Street to Lowell Street
- Continue installation of sanitary and water services south/west of 9th Street
- Install storm sewer main as weather allows

 

 

 

Roosevelt Avenue reconstruction
Roosevelt Avenue reconstruction
Roosevelt Avenue reconstruction
Roosevelt Avenue - 12th Street Intersection
Roosevelt Avenue
Roosevelt Avenue
Roosevelt Avenue
Roosevelt Avenue
Roosevelt Avenue
Roosevelt Avenue
Roosevelt Avenue
Roosevelt Avenue
Roosevelt laterals
Roosevelt storm sewer
Roosevelt storm main