Roosevelt Avenue - 6th Street to 12th Street Reconstruction
Project Type:
Street
Project Status:
Approved and Under Construction
Location:
Roosevelt Avenue
6th Street - 12th Street
Two Rivers,
WI
54241
See map: Google Maps
July 30, 2024 Update
-Completed water services and sanitary sewer laterals on July 29
-All properties are now on the new water main and temporary water service is currently being dismantled.
-Currently working on storm sewer main and storm service laterals. Expect to complete storm sewer work in the next two weeks.
-Grading and graveling operations are expected to start the week of August 12
July 8, 2024 Update
- Completed installation of sanitary sewer main (12th Street to Lowell Street)
- Continue installation of water main from 9th Street to Lowell Street
- Continue installation of sanitary and water services south/west of 9th Street
- Install storm sewer main as weather allows