Roosevelt Avenue - 6th Street to 12th Street Reconstruction
September 4, 2024 Update
- Completed underground utilities on August 8
- Completed grading and gravel operations on August 21
- Contractor placed portion of mainline pavement August 26.
- Remaining pavement is planned to be placed the week of September 9.
- Sidewalk and driveway replacement scheduled after completion of pavement.
**** Residents may take their garbage/recycling to the nearest intersection during this concrete paving process. ****
NOTE: Vehicular access will NOT be available along Roosevelt Avenue during paving and curing operations. This will be in effect through the month of September.
August 22, 2024 Update
- Completed underground utilities on August 8
- Completed grading and gravel operations on August 21
- Contractor scheduled to begin preparing for paving operations August 23
- Paving operations are expected to commence the week of August 26
NOTE: Vehicular access will NOT be available along Roosevelt Avenue during paving and curing operations. This will be in effect through the month of September.